What Is a Lien Waiver in Construction?
A lien waiver is a signed document in which a contractor, sub or supplier gives up some or all of its right to file a mechanics lien in exchange for payment. Collecting the right waiver with each payment is how you avoid paying for the same work twice.
Why lien waivers matter
Anyone who improves a property and goes unpaid can usually file a mechanics lien against it, even if you already paid the sub who hired them. A lien clouds the owner's title, holds up draws and closings, and often ends with the general contractor paying again to clear it. A lien waiver is the receipt that proves the right to lien was released.
The four types of lien waiver
- Conditional progress waiver. Releases lien rights for a progress payment only once that payment actually clears.
- Unconditional progress waiver. Releases lien rights for a progress payment immediately. Only sign or accept it once the funds have cleared.
- Conditional final waiver. Releases all lien rights on the job once the final payment clears.
- Unconditional final waiver. Releases all remaining lien rights immediately. Use it only after the final payment has cleared.
Our guide to conditional vs. unconditional lien waivers covers the differences in detail.
When to collect them
- Before you release a payment, collect a conditional waiver for that amount.
- After the payment clears, collect the unconditional waiver for the same amount.
- Collect waivers from lower-tier subs and major suppliers too, not just your direct subs.
- At the end of the job, swap to final waivers.
State rules
Several states, including California and Texas, require specific statutory waiver wording, and a waiver that doesn't follow it may not be enforceable. Check your state's rules with your attorney. Our free lien waiver form is a starting point for states without a required form.
Common mistakes
- Accepting an unconditional waiver before the check clears.
- Waivers whose "through date" or amount doesn't match the payment.
- Forgetting the lower-tier subs and suppliers.
- Waivers scattered across email, so nobody can tell which are missing.
This guide is general information, not legal advice. Lien law varies by state.
Frequently asked questions
What is a lien waiver?
A signed document in which a contractor, sub or supplier gives up some or all of its right to file a mechanics lien on a property in exchange for payment.
What is the difference between a conditional and an unconditional lien waiver?
A conditional waiver only takes effect once the payment clears. An unconditional waiver takes effect immediately, so it should only be signed after the money is received.